Case Study · Electrical & solar contracting

Zoho Projects for Electrical Contractors: From Spreadsheet Workload Plans to Live Job Costing and Capacity

How Techwave Solutions connected Zoho CRM, Zoho Projects and Zoho Analytics for ENPRO Energiearchitekten AG, so every won deal becomes a ready project, field hours drive job costing and management sees weeks ahead whether the team has room for the next order.

ClientENPRO Energiearchitekten AG
LocationSwitzerland
IndustryElectrical & solar contracting
Zoho appsZoho One: CRM, Projects, Analytics

Zoho Projects for Electrical Contractors: Deal to Debrief

One connected chain from the first enquiry to the post-calculation

Zoho CRM logoZoho CRM Zoho Projects logoZoho Projects Zoho Analytics logoZoho Analytics
1
Zoho CRM logo
Enquiry

Region, advisor, priority

2
Win

Offer accepted

3
Zoho Projects logo
Project

Built from a template

4
Hours

Logged on site

5
Debrief

Actual vs offer

6
Zoho Analytics logo
Capacity

Weeks ahead

Projects this week (sample)
PV 12 kWp, private houseMounting done · 38 of 46 h used
On budget
Sub-distribution, workshopWaiting for meter release
Delayed
Every project has
BudgetFrom offer
HoursFrom field
LessonBack in CRM
ENPRO Energiearchitekten AGElectrical & solar contracting, Switzerland
0 retypingA won deal becomes a project automatically
Field hoursTechnicians log time against tasks on the phone
Job costingBudgeted and actual hours side by side
Weeks aheadLoad forecast from deals, projects and team hours

Zoho Projects for electrical contractors answers three questions that a workload spreadsheet never answers reliably: how loaded the team is right now, which jobs are running over, and what a new order will do to the coming weeks. Installers share one crew across many parallel jobs, so a delay on one roof moves people on three other sites.

This case study shows how Techwave Solutions implemented Zoho One for ENPRO Energiearchitekten AG, a Swiss renewable energy company that runs PV and electrical installation projects with project managers and field technicians. It covers the problem, the design across Zoho CRM, Zoho Projects and Zoho Analytics, the build and what changed. Figures in the screens are sample data.

In brief

When every planner keeps a different workload file, nobody knows how busy the team is. At ENPRO, Zoho Projects for electrical contractors sits between sales and reporting: a won deal in Zoho CRM creates the project, technicians log hours on the phone and job costing runs per project. A debrief writes actuals back to the CRM, and Zoho Analytics turns deals and booked projects into capacity planning for the weeks ahead.

01
The challenge

The challenge: years of workload planning in spreadsheets

At ENPRO, workload had been planned in spreadsheets for years. Each project manager kept a file, each file had its own columns, and a few macros held the whole thing together until someone inserted a row in the wrong place. Jobs got entered twice, or not at all.

The CRM, project lists, time reports and forecast existed side by side, unconnected, so every question about next month started with copying numbers.

Fragile planning files

Different layouts per planner, macros that break, double or missing entries.

Unknown real load

Nobody knows how busy the technicians are next week, or what a new order means for the schedule.

Idle crews, busy office

Installers wait because a job slipped on a late delivery, while the office feels overloaded.

No post-calculation

Actual hours are rarely compared with the hours in the offer. So pricing never learns.

Before

Three sources, no shared plan

Sales, planning and hours each live in their own file

Legacy CRM
Offers and orders
Customer and deal
Not linked to jobs
Won date only
Zoho Sheet logoWorkload files
Planning
One file per planner
Double entries
Fragile macros
Time sheets
Hours
Paper and weekly lists
Which job, which task?
Over or under the offer?
Retyped project data
Load by gut feeling
No actual vs offer
PV systems Electrical installations Storage and charging
Techwave Solutions logo

Before: offers, planning files and time sheets are kept apart, so load and margin are guesses (illustration)

02
Root cause

Why electrical and solar installers lose sight of capacity

The work itself creates the problem. A PV job depends on things the contractor does not control: the panel and inverter delivery, the scaffolding date, the grid operator’s connection approval and the weather on mounting day. Any of these can push a job by a week, and the planned crew has to go somewhere else.

Meanwhile, sales keeps selling. An advisor closing three offers in a week cannot check whether technicians are free when the customer expects. Without a shared view, capacity planning comes down to the project managers meeting on Monday and comparing notes.

The second gap is learning. Offers for PV systems are usually priced on hours per kWp plus fixed blocks for electrical work and commissioning. If actual hours never flow back, the estimate never gets corrected, and job costing done once a year does not change the next quote.

03
The client

About ENPRO Energiearchitekten AG and why it chose Zoho

ENPRO Energiearchitekten AG is a renewable energy company in Switzerland. It plans and installs PV systems and electrical installations, runs many projects in parallel and works with project managers in the office and technicians on site.

Before choosing a system, ENPRO weighed a cleaner master spreadsheet against a standalone scheduling tool. The spreadsheet would still be typed by hand. The scheduling tool would show the crew calendar, but not the deals about to be won or the hours spent per task. The value was in the links: the won deal creates the project, the project collects the hours, and the hours feed both the margin and the forecast.

Zoho One keeps those links inside one account. Zoho CRM, Zoho Projects and Zoho Analytics share users and connect through built-in integrations and Deluge functions, so there is no export and import routine to maintain. That is why ENPRO chose Zoho Projects for electrical contractors: one chain of records, from first meeting to debrief, that every role reads from.

Client profile
CompanyENPRO Energiearchitekten AG
LocationSwitzerland
IndustryRenewable energy
WorkPV and electrical installations
TeamProject managers and technicians
FocusJob costing and capacity

Spreadsheets or a point tool

  • Project data retyped after each win
  • Hours collected weekly on paper
  • No link from actual hours to offers
  • Load forecast ignores the sales pipeline

Zoho CRM, Projects and Analytics

  • Project created from the won deal
  • Timesheets logged against tasks on site
  • Debrief figures written back to the CRM
  • Forecast combines deals, projects and hours
04
The solution

The solution design: Zoho Projects for electrical contractors, linked to sales and reporting

The design has six parts. Techwave Solutions confirmed the field list with ENPRO during discovery. Zoho CRM holds the commercial side, Zoho Projects holds the delivery side, and Zoho Analytics reads from both.

Zoho CRM logo

Enquiry and deal

Every enquiry with region, responsible advisor and priority, then deal stages from first meeting to won or lost.

Won deal to project

A Deluge function creates the project from the right template and copies customer, site and budgeted hours.

Zoho Projects logo

Project templates

Standard task lists for PV, storage and electrical jobs, each task with estimated hours.

Field timesheets

Technicians log hours on tasks in the Zoho Projects mobile app, on the day they work.

Project debrief

A short review at closure; actual hours per kWp and the deviation category go back to the deal.

Zoho Analytics logo

Load forecast

Open deals weighted by stage, booked projects and available team hours, week by week.

Deal to project

A won deal becomes a ready project

The project manager opens a task list, not a blank page

Zoho Projects for electrical contractors: main workflow viewDealWon
Private customer, PV 12 kWp
RegionRegion A
AdvisorAdvisor B
OfferVersion 2, 46 h budgeted
PriorityNormal
Deluge function
Zoho Projects for electrical contractors: team dashboardProjectTemplate: PV roof
2/5
Site visit and roof checkDone
Grid connection requestDone
Mounting and modulesNext week
Site address copied Budgeted hours per task Project manager assigned
Techwave Solutions logo

A won PV deal in Zoho CRM and the project created from it in Zoho Projects (illustration, sample data)

05
The implementation

The implementation: six steps from enquiry to debrief

Each step of Zoho Projects for electrical contractors at ENPRO is described by its trigger, its data and what happens next. People still decide prices, dates and crews. Automation does the copying and counting.

1

Every enquiry lands in Zoho CRM with an owner

Trigger: a call, a web form or an email from a prospective customer. Data: customer type, site address, region (canton), system size if known, responsible advisor and priority. Next: the advisor gets a first-contact task. Region matters later, because crews are planned by area.

2

Deal stages keep the offer history on one record

Trigger: the advisor books the first meeting. Data: stages for first meeting, offer, negotiation and won or lost, plus the offer value, budgeted hours and expected start month. Next: documents, emails and meeting notes stay on the deal, so anyone can see which offer version the customer accepted.

3

Won deal creates the project from a template

Trigger: the stage changes to won. Data: a workflow rule calls a Deluge function that reads the deal and creates a project in Zoho Projects from the matching template, such as PV roof, PV with storage or sub-distribution. Project name, customer, site address, offer details and budgeted hours are copied across, and the project ID is stored on the deal. Next: the project manager sees the full task list at once and only has to set dates and people.

Delivery chain

Four stages, one record trail

Every stage hands real data to the next one

1
Won

Offer and hours fixed

Zoho CRM logoZoho CRM
2
Planned

Tasks, dates, crew

Zoho Projects logoZoho Projects
3
On site

Hours on tasks

Zoho Projects logoMobile app
4
Debriefed

Actuals back to deal

Zoho CRM logoZoho CRM
Job costing runs the whole timeBudgeted hours from the offer, actual hours from the field, compared per task
Sales advisorProject managerTechnician
Techwave Solutions logo

The delivery chain from won deal to debrief across Zoho CRM and Zoho Projects (illustration)

4

Technicians log hours on tasks from the site

Trigger: a technician finishes work on a task, for example mounting rails or DC cabling. Data: hours, task, date and a short note, entered in the Zoho Projects mobile app. Hourly cost rates are set per user, so each entry carries a cost. Next: effort, progress and cost update on the project within minutes. Job costing becomes a running comparison of budgeted and actual hours and cost per project, so the project manager sees an overrun while the crew is still on the roof.

5

Project debrief writes the lesson back to the CRM

Trigger: the project manager sets the project to closed. Data: a short debrief covering planning quality, what deviated and a deviation category such as delivery delay, roof access, scope change or estimate too low. A Deluge function calculates actual hours per kWp from the timesheets and writes it, with the category, onto the original deal. Next: advisors can filter past deals by system type and region and price new offers on real figures.

6

Capacity planning from deals, projects and team hours

Trigger: a scheduled data sync from Zoho CRM and Zoho Projects into Zoho Analytics. Data: open deals with expected start month and budgeted hours, weighted by stage, plus remaining hours on booked projects and the available hours of each technician. Next: a weekly load chart shows when demand will exceed the team. Management can hire, move a start date or ask sales to offer later slots.

The stage weights in capacity planning are a business decision. A deal at first meeting counts for a small share of its hours, a deal in negotiation for most of them. The weights were agreed with ENPRO in discovery and are reviewed each quarter.

06
Reporting

Job costing and capacity planning reports in Zoho Analytics

Zoho Projects reports budget and timesheets per project. Zoho Analytics adds the cross-project view: all jobs, all crews and the sales pipeline, so job costing and capacity planning sit on one screen.

Zoho Analytics

Load and margin on one screen

Built from the same deals, projects and timesheets

ForecastNext 8 weeks
Job costingEvery project
Zoho Analytics logoInstallation load and job costs
Oct to Dec 2024All regions
Team hours1,040 hNext 4 weeks
Booked work880 hOpen projects
Weighted deals310 hBy stage
GapWeek 47Overload
Load vs team hours by week (sample)
Deviation categories
Delivery · Scope · Estimate
Actual hours per kWp, PV roof
PV 12 kWp, BernMounting38 / 46 hOn budget
Sub-distribution, workshopCabling31 / 28 hOver
PV with storage, FribourgPlanned4 / 64 hStarts wk 48
Techwave Solutions logo

Load forecast and job costing view in Zoho Analytics, sample hours and dates (illustration)

Reading the capacity planning chart

Each bar is one calendar week. The bar holds the remaining hours of booked projects plus the weighted hours of open deals expected to start that week. The dashed line is available team hours after holidays. A bar above the line is an overload; a bar well below it means idle crews. Because deals are part of the bar, the warning arrives while the offer is still open.

07
The results

The results: what changed for ENPRO

With the new setup in daily use, ENPRO reports projects that start from the won deal without retyping, hours logged on tasks from site, budget against actual on open jobs and a weekly view of crew load that includes the sales pipeline. These are operational changes, not measured financial results. The cards show how the team keeps checking each one.

Area
Before
With the solution
Project start
Job retyped from the offer
Project created from the won deal
Time recording
Weekly paper lists
Hours on tasks from the mobile app
Job costing
Rare, after invoicing
Budget vs actual on every open project
Pricing
Same estimates every season
Offers checked against debrief figures
Capacity planning
Monday meeting and gut feeling
Weekly forecast with deals included

Win to ready project

Compare the deal’s won date with the date the project manager assigns the first task.

Timesheet discipline

Count hours logged on the same day against hours entered later in the week. Job costing is only as current as the timesheets behind it.

Estimate accuracy

Track the gap between budgeted and actual hours for closed projects by system type, and watch it over time.

Idle and overload weeks

Record how many technician days were unplanned and how many weeks ran above team hours, then compare quarters.

08
Day to day

Day to day for each role

Four roles touch the system, and each sees only what it needs. Agreeing these roles with ENPRO before configuration is what keeps Zoho Projects for electrical contractors simple for the people on the roof.

Daily

Sales advisor

Works enquiries and deals in Zoho CRM, checks past hours per kWp when pricing and the load chart before promising a start month.

Daily

Project manager

Receives new projects with task lists already filled, sets dates and crews, watches budget against actual hours and runs the debrief at closure.

On site

Technician

Sees assigned tasks and site address in the mobile app, logs hours on the task worked, and notes what blocks a job.

Weekly

Management

Reviews the load forecast and the largest overruns, decides on hiring, subcontracting or rescheduling, and adjusts stage weights each quarter.

09
Delivery plan

Rollout timeline at ENPRO

The rollout ran in five phases. Dates and effort were set after discovery, once the templates were agreed.

PHASE 1

Discover

Map deal stages, job types, task lists, cost rates and stage weights.

PHASE 2

Migrate

Move open deals and running jobs out of the old CRM and planning files.

PHASE 3

Build

Templates, Deluge functions, timesheet rules and Analytics sync.

PHASE 4

Test

Sample deals through win, timesheets, closure and debrief.

PHASE 5

Pilot

One crew and its project manager first, then all teams.

Two phases needed extra care. The first was migration. Old planning files held the same job under different names, so running projects were matched to their deals before import. Double-counted jobs would have made the first forecast wrong.

The second was the mobile timesheet habit. Technicians were trained on a real job with their own phones. When hours came in late, the project manager saw gaps in the job costing view the same week. Capacity planning became reliable once that habit held across every crew.

10
FAQ

Zoho Projects for electrical contractors FAQ

Is Zoho Projects suitable for a small electrical or solar company?

Yes, when the company runs several jobs in parallel with a shared crew. Templates, timesheets and budgets cover delivery, and the CRM link removes retyping after each win.

How does job costing work in Zoho Projects?

Budgeted hours come from the offer and are set on the project and its tasks. Technicians log actual hours against tasks, cost rates turn hours into cost, and the project shows budget against actual at any time.

Can technicians log hours without a laptop?

Yes. The Zoho Projects mobile app lets them open their tasks, see the site address and log hours on the day

How is capacity planning calculated?

Zoho Analytics adds the remaining hours of booked projects to the open deals in Zoho CRM, weighted by stage, and compares the total with available team hours for each coming week.

Does the system price offers automatically?

No. Advisors price each offer, using actual hours per kWp that the debrief wrote back to past deals.

11
Work with us

How Techwave Solutions can help

Techwave Solutions is an Authorized Zoho Partner working with Zoho since 2015. We set up Zoho Projects for electrical contractors such as ENPRO and other project-based trades: project templates, Deluge functions from CRM to Projects, mobile timesheets, job costing views and capacity planning reports, with training on real jobs.

Learn more about Zoho Projects, see how billing on delivery works in our Zoho CRM and Zoho Projects integration guide, read about lead nurturing and site visits in Zoho One for solar installers, or book a free first call with a Zoho consultant to map your own project flow.

Talk to a Zoho consultant

Baliaghatta, Godagari, Rajshahi, Bangladesh
Get started

Choose the Zoho plan that fits your team

ENPRO’s setup uses CRM, Projects and Analytics together, which Zoho One covers in one licence. Zoho CRM Plus or Zoho CRM alone suit a sales-first start.

Best fit for this setup
Zoho One logo
ZohoOne

CRM, Projects, Analytics and Deluge in one suite

Sign up for Zoho One
Zoho CRM Plus logo
ZohoCRM Plus

CRM with Zoho Projects, marketing and analytics

Sign up for Zoho CRM Plus
Zoho CRM logo
ZohoCRM

Enquiries, deal stages and offers to start with

Sign up for Zoho CRM

Partner sign-up links from Techwave Solutions, an Authorized Zoho Partner.

Company background is as supplied by the client. No financial savings or percentage improvements are claimed in this case study; screen figures are sample data.