Zoho Projects for Electrical Contractors: From Spreadsheet Workload Plans to Live Job Costing and Capacity
How Techwave Solutions connected Zoho CRM, Zoho Projects and Zoho Analytics for ENPRO Energiearchitekten AG, so every won deal becomes a ready project, field hours drive job costing and management sees weeks ahead whether the team has room for the next order.
Zoho Projects for Electrical Contractors: Deal to Debrief
One connected chain from the first enquiry to the post-calculation
Enquiry
Region, advisor, priority
Win
Offer accepted
Project
Built from a template
Hours
Logged on site
Debrief
Actual vs offer
Capacity
Weeks ahead
Zoho Projects for electrical contractors answers three questions that a workload spreadsheet never answers reliably: how loaded the team is right now, which jobs are running over, and what a new order will do to the coming weeks. Installers share one crew across many parallel jobs, so a delay on one roof moves people on three other sites.
This case study shows how Techwave Solutions implemented Zoho One for ENPRO Energiearchitekten AG, a Swiss renewable energy company that runs PV and electrical installation projects with project managers and field technicians. It covers the problem, the design across Zoho CRM, Zoho Projects and Zoho Analytics, the build and what changed. Figures in the screens are sample data.
When every planner keeps a different workload file, nobody knows how busy the team is. At ENPRO, Zoho Projects for electrical contractors sits between sales and reporting: a won deal in Zoho CRM creates the project, technicians log hours on the phone and job costing runs per project. A debrief writes actuals back to the CRM, and Zoho Analytics turns deals and booked projects into capacity planning for the weeks ahead.
Table of contents
The challenge: years of workload planning in spreadsheets
At ENPRO, workload had been planned in spreadsheets for years. Each project manager kept a file, each file had its own columns, and a few macros held the whole thing together until someone inserted a row in the wrong place. Jobs got entered twice, or not at all.
The CRM, project lists, time reports and forecast existed side by side, unconnected, so every question about next month started with copying numbers.
Fragile planning files
Different layouts per planner, macros that break, double or missing entries.
Unknown real load
Nobody knows how busy the technicians are next week, or what a new order means for the schedule.
Idle crews, busy office
Installers wait because a job slipped on a late delivery, while the office feels overloaded.
No post-calculation
Actual hours are rarely compared with the hours in the offer. So pricing never learns.
Three sources, no shared plan
Sales, planning and hours each live in their own file
Customer and deal
One file per planner
Paper and weekly lists
Before: offers, planning files and time sheets are kept apart, so load and margin are guesses (illustration)
Why electrical and solar installers lose sight of capacity
The work itself creates the problem. A PV job depends on things the contractor does not control: the panel and inverter delivery, the scaffolding date, the grid operator’s connection approval and the weather on mounting day. Any of these can push a job by a week, and the planned crew has to go somewhere else.
Meanwhile, sales keeps selling. An advisor closing three offers in a week cannot check whether technicians are free when the customer expects. Without a shared view, capacity planning comes down to the project managers meeting on Monday and comparing notes.
The second gap is learning. Offers for PV systems are usually priced on hours per kWp plus fixed blocks for electrical work and commissioning. If actual hours never flow back, the estimate never gets corrected, and job costing done once a year does not change the next quote.
About ENPRO Energiearchitekten AG and why it chose Zoho
ENPRO Energiearchitekten AG is a renewable energy company in Switzerland. It plans and installs PV systems and electrical installations, runs many projects in parallel and works with project managers in the office and technicians on site.
Before choosing a system, ENPRO weighed a cleaner master spreadsheet against a standalone scheduling tool. The spreadsheet would still be typed by hand. The scheduling tool would show the crew calendar, but not the deals about to be won or the hours spent per task. The value was in the links: the won deal creates the project, the project collects the hours, and the hours feed both the margin and the forecast.
Zoho One keeps those links inside one account. Zoho CRM, Zoho Projects and Zoho Analytics share users and connect through built-in integrations and Deluge functions, so there is no export and import routine to maintain. That is why ENPRO chose Zoho Projects for electrical contractors: one chain of records, from first meeting to debrief, that every role reads from.
Spreadsheets or a point tool
- Project data retyped after each win
- Hours collected weekly on paper
- No link from actual hours to offers
- Load forecast ignores the sales pipeline
Zoho CRM, Projects and Analytics
- Project created from the won deal
- Timesheets logged against tasks on site
- Debrief figures written back to the CRM
- Forecast combines deals, projects and hours
The solution design: Zoho Projects for electrical contractors, linked to sales and reporting
The design has six parts. Techwave Solutions confirmed the field list with ENPRO during discovery. Zoho CRM holds the commercial side, Zoho Projects holds the delivery side, and Zoho Analytics reads from both.
Enquiry and deal
Every enquiry with region, responsible advisor and priority, then deal stages from first meeting to won or lost.
Won deal to project
A Deluge function creates the project from the right template and copies customer, site and budgeted hours.
Project templates
Standard task lists for PV, storage and electrical jobs, each task with estimated hours.
Field timesheets
Technicians log hours on tasks in the Zoho Projects mobile app, on the day they work.
Project debrief
A short review at closure; actual hours per kWp and the deviation category go back to the deal.
Load forecast
Open deals weighted by stage, booked projects and available team hours, week by week.
A won deal becomes a ready project
The project manager opens a task list, not a blank page
Private customer, PV 12 kWp
A won PV deal in Zoho CRM and the project created from it in Zoho Projects (illustration, sample data)
The implementation: six steps from enquiry to debrief
Each step of Zoho Projects for electrical contractors at ENPRO is described by its trigger, its data and what happens next. People still decide prices, dates and crews. Automation does the copying and counting.
Every enquiry lands in Zoho CRM with an owner
Trigger: a call, a web form or an email from a prospective customer. Data: customer type, site address, region (canton), system size if known, responsible advisor and priority. Next: the advisor gets a first-contact task. Region matters later, because crews are planned by area.
Deal stages keep the offer history on one record
Trigger: the advisor books the first meeting. Data: stages for first meeting, offer, negotiation and won or lost, plus the offer value, budgeted hours and expected start month. Next: documents, emails and meeting notes stay on the deal, so anyone can see which offer version the customer accepted.
Won deal creates the project from a template
Trigger: the stage changes to won. Data: a workflow rule calls a Deluge function that reads the deal and creates a project in Zoho Projects from the matching template, such as PV roof, PV with storage or sub-distribution. Project name, customer, site address, offer details and budgeted hours are copied across, and the project ID is stored on the deal. Next: the project manager sees the full task list at once and only has to set dates and people.
Four stages, one record trail
Every stage hands real data to the next one
Won
Offer and hours fixed
Planned
Tasks, dates, crew
On site
Hours on tasks
Debriefed
Actuals back to deal
The delivery chain from won deal to debrief across Zoho CRM and Zoho Projects (illustration)
Technicians log hours on tasks from the site
Trigger: a technician finishes work on a task, for example mounting rails or DC cabling. Data: hours, task, date and a short note, entered in the Zoho Projects mobile app. Hourly cost rates are set per user, so each entry carries a cost. Next: effort, progress and cost update on the project within minutes. Job costing becomes a running comparison of budgeted and actual hours and cost per project, so the project manager sees an overrun while the crew is still on the roof.
Project debrief writes the lesson back to the CRM
Trigger: the project manager sets the project to closed. Data: a short debrief covering planning quality, what deviated and a deviation category such as delivery delay, roof access, scope change or estimate too low. A Deluge function calculates actual hours per kWp from the timesheets and writes it, with the category, onto the original deal. Next: advisors can filter past deals by system type and region and price new offers on real figures.
Capacity planning from deals, projects and team hours
Trigger: a scheduled data sync from Zoho CRM and Zoho Projects into Zoho Analytics. Data: open deals with expected start month and budgeted hours, weighted by stage, plus remaining hours on booked projects and the available hours of each technician. Next: a weekly load chart shows when demand will exceed the team. Management can hire, move a start date or ask sales to offer later slots.
The stage weights in capacity planning are a business decision. A deal at first meeting counts for a small share of its hours, a deal in negotiation for most of them. The weights were agreed with ENPRO in discovery and are reviewed each quarter.
Job costing and capacity planning reports in Zoho Analytics
Zoho Projects reports budget and timesheets per project. Zoho Analytics adds the cross-project view: all jobs, all crews and the sales pipeline, so job costing and capacity planning sit on one screen.
Load and margin on one screen
Built from the same deals, projects and timesheets
Load forecast and job costing view in Zoho Analytics, sample hours and dates (illustration)
Reading the capacity planning chart
Each bar is one calendar week. The bar holds the remaining hours of booked projects plus the weighted hours of open deals expected to start that week. The dashed line is available team hours after holidays. A bar above the line is an overload; a bar well below it means idle crews. Because deals are part of the bar, the warning arrives while the offer is still open.
The results: what changed for ENPRO
With the new setup in daily use, ENPRO reports projects that start from the won deal without retyping, hours logged on tasks from site, budget against actual on open jobs and a weekly view of crew load that includes the sales pipeline. These are operational changes, not measured financial results. The cards show how the team keeps checking each one.
Win to ready project
Compare the deal’s won date with the date the project manager assigns the first task.
Timesheet discipline
Count hours logged on the same day against hours entered later in the week. Job costing is only as current as the timesheets behind it.
Estimate accuracy
Track the gap between budgeted and actual hours for closed projects by system type, and watch it over time.
Idle and overload weeks
Record how many technician days were unplanned and how many weeks ran above team hours, then compare quarters.
Day to day for each role
Four roles touch the system, and each sees only what it needs. Agreeing these roles with ENPRO before configuration is what keeps Zoho Projects for electrical contractors simple for the people on the roof.
Sales advisor
Works enquiries and deals in Zoho CRM, checks past hours per kWp when pricing and the load chart before promising a start month.
Project manager
Receives new projects with task lists already filled, sets dates and crews, watches budget against actual hours and runs the debrief at closure.
Technician
Sees assigned tasks and site address in the mobile app, logs hours on the task worked, and notes what blocks a job.
Management
Reviews the load forecast and the largest overruns, decides on hiring, subcontracting or rescheduling, and adjusts stage weights each quarter.
Rollout timeline at ENPRO
The rollout ran in five phases. Dates and effort were set after discovery, once the templates were agreed.
Discover
Map deal stages, job types, task lists, cost rates and stage weights.
Migrate
Move open deals and running jobs out of the old CRM and planning files.
Build
Templates, Deluge functions, timesheet rules and Analytics sync.
Test
Sample deals through win, timesheets, closure and debrief.
Pilot
One crew and its project manager first, then all teams.
Two phases needed extra care. The first was migration. Old planning files held the same job under different names, so running projects were matched to their deals before import. Double-counted jobs would have made the first forecast wrong.
The second was the mobile timesheet habit. Technicians were trained on a real job with their own phones. When hours came in late, the project manager saw gaps in the job costing view the same week. Capacity planning became reliable once that habit held across every crew.
Zoho Projects for electrical contractors FAQ
Is Zoho Projects suitable for a small electrical or solar company?
Yes, when the company runs several jobs in parallel with a shared crew. Templates, timesheets and budgets cover delivery, and the CRM link removes retyping after each win.
How does job costing work in Zoho Projects?
Budgeted hours come from the offer and are set on the project and its tasks. Technicians log actual hours against tasks, cost rates turn hours into cost, and the project shows budget against actual at any time.
Can technicians log hours without a laptop?
Yes. The Zoho Projects mobile app lets them open their tasks, see the site address and log hours on the day
How is capacity planning calculated?
Zoho Analytics adds the remaining hours of booked projects to the open deals in Zoho CRM, weighted by stage, and compares the total with available team hours for each coming week.
Does the system price offers automatically?
No. Advisors price each offer, using actual hours per kWp that the debrief wrote back to past deals.
How Techwave Solutions can help
Techwave Solutions is an Authorized Zoho Partner working with Zoho since 2015. We set up Zoho Projects for electrical contractors such as ENPRO and other project-based trades: project templates, Deluge functions from CRM to Projects, mobile timesheets, job costing views and capacity planning reports, with training on real jobs.
Learn more about Zoho Projects, see how billing on delivery works in our Zoho CRM and Zoho Projects integration guide, read about lead nurturing and site visits in Zoho One for solar installers, or book a free first call with a Zoho consultant to map your own project flow.
Talk to a Zoho consultant
Choose the Zoho plan that fits your team
ENPRO’s setup uses CRM, Projects and Analytics together, which Zoho One covers in one licence. Zoho CRM Plus or Zoho CRM alone suit a sales-first start.